NEW QUESTION # 43
Your organization has a requirement to send notifications to the owners of the associated tasks when the status of a deliverable is set to Complete. You have been asked to evaluate generate public events for project deliverable status changes feature to manage this requirement.
Which two statements are true about this feature? (Choose two.)
- A. The public event is not generated when the priority of a deliverable changes.
- B. The public event is not generated when a deliverable is created or deleted.
- C. The public event is generated when the progress status for a deliverable changes.
- D. The public event is generated when a deliverable is created or deleted.
Answer: B,C
Explanation:
The generate public events for project deliverable status changes feature is a feature that allows you to send notifications or trigger actions when the progress status of a deliverable changes from one value to another. For example, when the status of a deliverable is set to Complete, you can send a notification to the owners of the associated tasks or update the status of the tasks accordingly. Two statements that are true about this feature are:
The public event is not generated when a deliverable is created or deleted. This feature only generates events when the progress status of a deliverable changes, not when a deliverable is added or removed from a project or task.
The public event is generated when the progress status for a deliverable changes. This feature generates events when the progress status of a deliverable changes from one value to another, such as from Not Started to In Progress, or from In Progress to Complete. You can define rules and actions for each progress status change using Business Process Management (BPM) Worklist. The public event is also not generated when the priority of a deliverable changes, as this feature only generates events when the progress status of a deliverable changes. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-execution.html#OAPFM2356211
NEW QUESTION # 44
You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)
- A. The organization is classified as a project unit.
- B. The organization is not classified as a project expenditure organization.
- C. The organization is not included in the organization tree that is assigned to the business unit that owns the PO.
- D. The organization is not classified as a project-owning organization.
Answer: B,C
Explanation:
Ref: Implementing-Project-Financial-Management-and-Grants-Management.pdf Chapter 3 - Define Project Organizations Page # 12 Topic - Selecting Organization Hierarchies for the Business Unit The following conditions are required for an organization to be eligible to be a project expenditure organization:
You must assign the Project Expenditure Organization classification to the organization.
The organization must belong to the hierarchy that you specify in the project implementation options for the business unit.
NEW QUESTION # 45
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)
- A. Cost
- B. Effort
- C. Manual Entry
- D. Remaining Plan
Answer: A
Explanation:
Reference https://ppm-help.saas.hpe.com/en/9.42/Help/Content/UG/PjMUG/view_pj_cost_data_costtab.htm Below is an example of the Financial Summary view on the Cost tab of the Project Overview page.
NEW QUESTION # 46
Which three are valid password complexity criteria while setting up password policies? (Choose three.)
- A. Very Complex: At least 8 characters, 1 uppercase, 1 number, and 2 special characters
- B. Simple: At least 8 characters and 1 number
- C. Complex: At least 8 characters, 1 uppercase, and 1 number
- D. Very Complex: At least 8 characters, 1 uppercase, 1 number, and 1 special character
- E. Very Complex: At least 6 characters, 1 uppercase, 1 number, and 1 special character
Answer: A,C,D
NEW QUESTION # 47
A consulting services company is currently working on a business transformation project for your client, which spans multiple years. At the first period close, the consulting services company has recognized revenue and the accounting entry created is:
Dr Unbilled Receivables 40,000
Cr Revenue 40,000
At the end of the period, the client is sent an associated bill. What would be the corresponding invoice accounting entry? (Choose the best answer.)
- A. Dr Accounts Receivables 40,000Cr Unbilled Receivables 40,000
- B. Dr Accounts Receivables 40,000Cr Revenue 40,000
- C. Dr Unearned Revenue 40,000Cr Revenue 40,000
- D. Dr Unearned Revenue 40,000Cr Accounts Receivables 40,000
Answer: A
Explanation:
When the invoice is created, the unbilled receivables balance is reduced and the accounts receivables balance is increased by the invoice amount. This is because the revenue has already been recognized and the invoice is just a request for payment from the customer. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/project-accounting.html#OAPFM2355710
NEW QUESTION # 48
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y - Task 30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)
- A. Bill set number drives the grouping of transactions.
- B. Both the contract lines create only a single invoice because they are using the same contract.
- C. Invoice generation does not depend on bill plan. The invoices are created based on the contract line.
- D. Two invoices are created using the same contract.
Answer: A,D
Explanation:
Ref: https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJB/F1087456AN1006D.htm What's a bill set?
Transactions originating from different bill plans with the same bill set number on a contract are included on the same invoice. If a contract has multiple bill plans and each have different values for the bill set, Oracle Fusion Project Billing creates a separate invoice for each bill plan
NEW QUESTION # 49
You are implementing Project Portfolio Management for a global professional services organization. In their Consulting Services line of business, it is common to use resources from different business units based on the skills required. Therefore, cross-charge transactions happen between business units within the same legal entity. Transfer price calculations need to be based on raw costs, with no further adjustments to transfer price.
Identify two setups that can drive this borrowed and lent agreement. (Choose two.)
- A. A document entry such as straight time must be enabled for cross-charge transactions.
- B. Transfer price basis must be Burdened Cost, and calculation method must be Burden Rate Schedule.
- C. Transfer price basis must be Raw Cost and calculation method must be Basis Only.
- D. Transfer price basis must be Raw Cost and calculation method must be Rate Schedule.
Answer: A,C
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-billing-configuration-define-transfer-pricing.html#OAPFM3094619
NEW QUESTION # 50
Your customer wants additional project information for detailed account balance maintenance, reconciliation, and reporting. Identify the configuration in subledger accounting that can be set up to fulfill this requirement. (Choose the best answer.)
- A. Supporting Reference
- B. Accounting Method
- C. Accounting Rule
- D. Journal Rules
- E. Mapping Sets
Answer: A
Explanation:
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/OAPFM/OAPFM1125357.htm#OAPFM1125357 Assignment of Supporting Reference Supporting references may be used to capture transaction values on journal entry lines. A supporting reference can be used on a journal entry rule set only if it's assigned a source from the event class of the journal entry rule set.
Creating Supporting Reference: Explained
Supporting references are used to store additional source information about a subledger journal entry at the line level.
Supporting references with balances establish subledger balances for a particular source and account for a particular combination of supporting references plus the account combination.
For example:
If a journal line contains a supporting reference that includes two sources, Customer Type and Customer Name.
Balances are created for the account combination, plus customer name and customer type.
Examples of how you may want to use supporting reference balances are to:
Facilitate reconciliation back to the subledgers and source systems by tagging journal entries with transaction and reference attributes.
Create balances by dimensions not captured in the chart of accounts.
Reporting using dimensions not captured in the chart of accounts.
Enrich Oracle Fusion Business Intelligence Applications reporting on subledger journals.
Profit and loss balances by dimensions not captured in the chart of accounts Define supporting references to hold additional supporting information for detailed account balance maintenance or reconciliation and reporting requirements.
NEW QUESTION # 51
Which application generates external roles to grant both function and data security? (Choose the best answer.)
- A. Functional Setup Manager
- B. Authorization Policy Manager
- C. Oracle Identity Manager
- D. Business Process Manager
Answer: C
Explanation:
Authorization Policy Manager (APM)
APM greatly simplifies the creation, configuration, and administration of application policies APM does not support the management of users and external roles; these artifacts can only be viewed with the tool. Their provision and management is typically accomplished using Oracle Identity Manager Oracle Identity Manager (OIM) In regard to enterprise users and external roles, Authorization Policy Manager provides viewing and searching functionality only. To manage users and external roles, use Oracle Identity Manager or some other identity management tool.
OIM provision users, roles, and defines what a user can do in Oracle Cloud Duty Roles are mapped to jobs and assigned access privileges (Data Security)
NEW QUESTION # 52
When implementing Project Performance Reporting, your customer has the following requirements:
Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
- A. multiple threshold levels
- B. multiple threshold level value
- C. single threshold level range
- D. single threshold level value
Answer: D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjs/update-project-performance-data-and-generate-kpis.html#OAPJS16654 Performance Status Indicator Performance status indicators give an immediate picture of the status of a project, such as critical, at risk, and on track. Each distinct icon indicates the status and severity of performance. During KPI definition, you first associate status indicators with performance statuses:
Critical
Severe
At risk
On track
Ahead
You then associate these statuses with threshold levels. When KPI values are generated for a project, each value is compared to the defined thresholds and the corresponding status indicator for the KPI appears on project performance reports.
A status can identify negative performance so that you can take the appropriate actions to prevent or quickly resolve problems. Conversely, a status can identify positive performance to help you track expected or excellent performance.
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/fapfm/implementing-project-financial-management-applications.html#FAPFM975706 Create Key Performance Indicators Create key performance indicators (KPI) to measure how well your organization performs an operational, tactical, or strategic activity that is critical for the current and future success of the organization.
Note: To create KPIs you must enable a project unit to track key performance indicators.
Use the Threshold Levels section to specify thresholds to indicate the health status of a KPI. Select one of the following options:
Multiple threshold levels
Single threshold level value
Single threshold level range
NEW QUESTION # 53
Your customer has a requirement to import and process third-party transactions that are "costed" and "accounted".
Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)
- A. Document Entry Options
- B. Import Options
- C. Transaction Source Options
- D. Document Options
Answer: C
Explanation:
Reference https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJC/F1071488AN1004C.htm
NEW QUESTION # 54
You are now the project manager of a newly created implementation project. Which two items are not part of managing an implementation project?
- A. Generate a list of setup tasks.
- B. Select the offering you want to implement.
- C. Assign tasks to various users who are responsible for managing setup data.
- D. Monitor the progress of completing setup tasks.
- E. Enable optional functional areas and features by opting in.
Answer: B,E
Explanation:
Selecting the offering you want to implement and enabling optional functional areas and features by opting in are not part of managing an implementation project. These are part of configuring an implementation project, which is done before managing an implementation project. Configuring an implementation project allows you to define the scope and features of your implementation based on your business needs. Managing an implementation project involves assigning tasks to various users who are responsible for managing setup data, monitoring the progress of completing setup tasks, and generating a list of setup tasks. These are part of executing an implementation project, which is done after configuring an implementation project. Executing an implementation project allows you to perform the setup tasks and validate the setup data for your implementation. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/implement-project-financial-management-applications.html#OAPFM2356021
NEW QUESTION # 55
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security. (Choose two.)
- A. Project Accountant Template for Project Organization Security
- B. Project Billing Specialist Template for Project Organization Security
- C. Project Administrator Template for Project Organization Security
- D. Project Manager Template for Project Organization Security
- E. Project Creator Template for Project Organization Security
Answer: C,E
Explanation:
Reference https://docs.oracle.com/en/cloud/saas/applications-common/r13-update17d/faser/implementing-security-in-oracle-fusion-project-portfolio-management.html#FASER1722595 Ref to "Securing Project Financial Management and Grants Management Applications" Table lists predefined enterprise roles and the type of security that grants the role access to data in a work area or dashboard.
Enterprise Role
Work Area or Dashboard
Data Security Based On
Project Accountant
Asset
Project business unit
Project Accountant
Costs
Project expenditure business unit
Project Accountant
Revenue
Contract business unit
Project Administrator
Project Financial Management
Project business unit
Project organization
Project Billing Specialist
Invoices
Contract business unit
Project Creator
Project Financial Management
Project business unit
Project organization
Project Management Duty
Project Management Infolet Dashboard
Project assignment
Project Management Duty
Project Performance Dashboard
Project assignment
Project Manager
Project Management Infolet Dashboard
Project assignment
Project Manager
Project Performance Dashboard
Project assignment
Project Manager
Project Management
Project assignment
Project Manager
Project Manager Dashboard
Project assignment
Project Team Member
Project Financial Management
Project assignment
Grants Accountant
Invoices
Contract business unit
Grants Accountant
Revenue
Contract business unit
Grants Administrator
Awards
Contract business unit
Grants Administrator
Contracts
Contract business unit
Grants Administrator
Project Financial Management
Project business unit
Principal Investigator
Awards
Award assignment
Principal Investigator
Contracts
Award assignment
Principal Investigator
Project Financial Management
Project assignment
NEW QUESTION # 56
Which three can be tracked as Status tracking for Project Invoice Approval Notifications? (Choose three.)
- A. Prior actions
- B. Person assigned for approval
- C. Date-wise updates to the document
- D. Pre-approval activities
- E. Persons with whom it is still pending approval
Answer: A,B,E
Explanation:
Status tracking is a feature that allows you to track the progress and history of project invoice approval notifications. Status tracking provides information such as who approved or rejected the invoice, when and why they took the action, who is currently assigned to approve or reject the invoice, etc. Three of the information that can be tracked as status tracking for project invoice approval notifications are:
Person assigned for approval: This shows the name of the person who is currently assigned to approve or reject the invoice notification.
Prior actions: This shows the list of actions that have been taken on the invoice notification by previous approvers or rejectors, such as approve, reject, request information, etc.
Persons with whom it is still pending approval: This shows the list of persons who are still in the approval chain for the invoice notification and have not taken any action yet. Pre-approval activities and date-wise updates to the document are not information that can be tracked as status tracking for project invoice approval notifications. Pre-approval activities are tasks that need to be performed before submitting an invoice for approval, such as validating or transferring the invoice. Date-wise updates to the document are changes that are made to the invoice document after it has been submitted for approval, such as adjusting or reversing the invoice. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-invoices.html#OAPFM2356291
NEW QUESTION # 57
Green House Corporation has decided to enable the budgetary control feature for their projects. At which two levels will they be able to enter the amounts in the budget versions for these projects?
(Choose two.)
- A. Top resource
- B. Expenditure Type
- C. Expenditure Category
- D. Project
- E. Task
Answer: D,E
Explanation:
Budgetary control is a feature that allows you to monitor and control project costs against approved budgets. You can enter the amounts in the budget versions for these projects at two levels: Task and Project. These levels correspond to the budgetary control levels that are defined for the project type. You can also view and compare the budget amounts and actual costs at these levels using reports and dashboards. Expenditure Type, Top Resource, and Expenditure Category are not levels at which you can enter the amounts in the budget versions for these projects. These are attributes that can be used to group and filter the budget and actual amounts for reporting purposes. Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-budgets-and-forecasts.html#OAPFM2356191
NEW QUESTION # 58
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)
- A. Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
- B. Summarized actual quantity and cost flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- C. Projects and task definitions flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- D. Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
- E. Event completion flows from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
Answer: B,C,E
Explanation:
Ref: https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125394AN6D254.htm Primavera P6 Enterprise Project Portfolio Management and Oracle Fusion Project Portfolio Management: How They Work Together Use Oracle Fusion Project Integration Gateway to integrate Oracle Fusion Project Portfolio Management with Primavera P6 Enterprise Project Portfolio Management. The integration enables project accountants, project billing specialists, and executives to centrally perform project costing, billing, accounting, and executive reporting tasks in Oracle Fusion Project Portfolio Management while enabling each project manager to perform detailed project planning and scheduling in Primavera P6 Enterprise Project Portfolio Management.
Oracle Fusion Project Integration Gateway ensures data security, integrity, and efficiency by defining a set framework in which data is exported from and imported into Oracle Fusion Project Portfolio Management.
The following table and diagram provide an overview of the flow of information.
Information Type
From Application
To Application
Global integration information
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Projects and task definition
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Summarized project actual quantity and cost
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Project plans and progress
Primavera P6 Enterprise Project Portfolio Management
Oracle Fusion Project Portfolio Management
Billing events
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Event completion
Primavera P6 Enterprise Project Portfolio Management
Oracle Fusion Project Portfolio Management
NEW QUESTION # 59
......